The short version: At FNA, most app projects take around two months, depending on size. An app with payments, several user roles and integrations takes longer. Be wary of any firm date given before the scope is written down.
This guide explains how long app development takes for a business in the UAE: the phases from scope to app store review, what adds time here in particular, how to tell whether a timeline you have been quoted is realistic, how to put a launch date in a contract, and how to get a first version out sooner.
We are FNA Technology, an app development company with our team in Mumbai, India, and we build iPhone and Android apps for UAE businesses remotely. If you already know you want an app built, see our mobile app development in Dubai.
Why there is no single answer
How long an app takes depends on what it has to do, not on what it is called. Two "booking apps" can differ by months: one shows a calendar and takes a form, the other handles payments, staff schedules, reminders, cancellations, an admin panel and a link to your accounting system. The time goes into the number of user roles, screens, rules, integrations and the testing all of that needs.
That is why a firm date given from a one-line description is a guess. A believable timeline only comes after someone has written down what the app will and will not do.
The phases of an app project
| Phase | What happens | What makes it longer |
|---|---|---|
| Scope | Users, features, platforms, integrations and what is out of the first version are written down | Many stakeholders, or nobody with authority to decide |
| Design | User flows, wireframes and screens, approved before building | Arabic and English layouts, slow feedback, late changes |
| Build | The app, the backend, the admin panel and the integrations | More user roles, payments, live tracking, chat, links to other systems |
| Testing | Bugs, devices, payments, security and real user journeys | Many devices, both languages, integrations that are hard to test |
| Store review | Apple App Store and Google Play check the app before release | A rejection that needs a fix and resubmission |
Phases overlap in a well-run project: the backend starts while the last screens are designed, and testing runs alongside the build rather than only at the end.
What adds time in the UAE
- Arabic and English: screens designed for both languages with right-to-left layouts take more design and testing than an English-only app
- UAE PASS sign-in: integration needs approval from the UAE PASS onboarding team, which the developer does not control, so plan for it early
- Local payment gateways and other integrations: they usually take longer than the screens, because they depend on third-party sandboxes, credentials and approvals that neither side fully controls
- Data rules: if your sector or your customers require where data is hosted, that has to be decided before the backend is built
- Content: Arabic and English text, product data, legal pages and app store screenshots are often what holds up the final weeks
Is the timeline you were quoted realistic?
A realistic timeline can be explained phase by phase. Ask for the plan behind the date and check for these:
- The scope is written down: features, user roles, platforms and integrations, and what is left for later
- Design is approved before the build starts
- Testing has its own time, including Arabic screens and real devices
- App store review is in the plan, with room for one resubmission
- Your responsibilities are listed: content, accounts, approvals and how fast you give feedback
- Integrations that need someone else's approval are named, with a note on what happens if they are slow
Red flags: a firm date before anyone has asked about your users or integrations, a plan that goes straight from coding to launch day, or a complex app with payments and many user roles promised in a few weeks. Ask what has been left out to make the date fit.
Putting a launch date in the contract
"We deliver in ten weeks" in a proposal is not the same as a date in a contract. If the date matters, for example because of an event or a season, agree in writing:
- What "launch" means: a build you can test, submission to the stores, or the app live for the public
- The milestone dates for design sign-off, a feature-complete build, testing and store submission
- A scope-freeze date, after which changes are priced and dated separately
- What you must provide, and by when, for the date to hold
- What happens if the company causes the delay
- How app store review delays are treated, since neither side controls them
How to get a first version out sooner
- Cut the first version to one main user journey that proves people will use the app
- Build it cross-platform, in one codebase for iPhone and Android, unless the app depends on special phone features; our guide to native vs cross-platform app development explains the choice
- Decide on platforms, user roles and integrations before design starts
- Approve designs in batches, and have one person on your side who can say yes
- Open the Apple and Google developer accounts in week one; a company needs a D-U-N-S Number for Apple, and Apple says to allow up to 5 business days to receive it and up to 2 more for Apple to receive the details
- Prepare content and legal pages while the app is being built
- Plan the second release now, so "not in version one" does not mean "never"
App store review
Both stores check an app before it goes live. Apple says it typically reviews at least 50% of submissions in less than 24 hours and 90% in less than 48 hours. Google says reviews for some developer accounts can take up to seven days, or longer in exceptional cases. A rejection means a fix and a resubmission, so leave room for one in the plan, and submit early enough that a review delay does not move a fixed launch event.
How long our app projects take
At FNA, most projects take around two months, depending on size, and before the full build we can make a working demo or proof of concept of your problem in one day. We build one cross-platform app in React Native or Flutter, or native apps in Swift and Kotlin, whichever fits the project, with Arabic and English screens designed together when you need both. After discovery you get a dated plan, and you own the source code and the app store listings. For businesses in Saudi Arabia, see our mobile app development in Saudi Arabia.
Plan Your App
Mobile App Development in Dubai
iOS and Android apps for UAE businesses, with Arabic right-to-left layouts, built remotely from Mumbai.
Mobile App Development in Saudi Arabia
Arabic and English apps for Saudi businesses, cross-platform or native.
MVP Development
A focused first version of a new product, scoped to test one assumption.
Frequently Asked Questions
It depends on what the app must do. A focused first version with a few core screens and few integrations is far quicker than an app with payments, several user roles, an admin panel and links to other systems. At FNA, most projects take around two months, depending on size.
Integrations that need someone else's approval, such as UAE PASS or a payment gateway, slow decisions on your side, and scope that grows after design is signed off. Arabic and English screens with right-to-left layouts also add design and testing work.
Apple says it reviews at least half of submissions in under 24 hours and 90% in under 48 hours. Google says reviews for some developer accounts can take up to seven days, or longer in exceptional cases, and a rejection on either store adds a fix and resubmit cycle.
Some will commit to a date once the scope is fixed after discovery, but the public launch also depends on app store review and on things you provide, such as content and approvals. Agree in writing what "launch" means, what moves the date, and what happens if the company causes the delay.
Cut the first version to one main user journey, build it cross-platform if the app does not need special phone features, and give feedback on designs quickly. Adding developers late usually adds handover and coordination before it adds speed.
Usually, because one codebase runs on both iPhone and Android, so most screens are built and tested once. Planning, the backend, integrations and store review take the same time either way.